Themes
Portsmouth Dockyard
-
Learning
Shipwrights
Page 1 of 2
Shipwrights were the senior trade in the dockyard. They controlled most of the work which went on in the dockyard. They were responsible for the watertight integrity of the ship. Shipwrights worked on the structure of the ship originally in wood and later in metal. Most of the internal fittings came under the shipwrights.
Shipwrights built the internal ship fittings such as mess lockers. Other trades worked inside the ships such as plumbers and electricians. They had control of the compartments they were working in. If they wanted to come out of the compartment, or go up, down or through the decks, they had to get the sanction of the shipwrights. This meant that shipwrights were in control of everything that went on.
Changes in shipbuilding meant that over the twentieth century the everyday work of the shipwright changed. At the beginning of the twentieth century riveted ships were the norm. However, after the second world war welding had developed to such a high standard that welded ships superseded riveted ships. The technique of constructing riveted ships is completely different to welded ships. A riveted ship is built with frames or ribs. Shipwrights manufacture welded ships using long beams which travel the length of the ship making it stronger. Welders construct pre-fabricated units in workshops. The shipwrights assemble all the units on the slipway and launch the ship once it is complete.
To hear a shipwright describe how ships were built select the oral history extract below:
Get the Flash Player to see this player.
Transcript:
"I had 3 or 4 charge men there building different sections of the ship. All built in sections in weldments, certain sections you can build up, then you weld them together and then lifted them by the crane and put them on the slip in their sections. Various weights.
Interviewer: You didn't build a whole hull in one go
Not in one, no. we built them in weldments, in sections there was the bow section, the second one and third and fourth, stern section and so on, then the superstructure. All built in sections.
Interviewer: What would be laid down first? Which part the middle part?
You had the keel section first obviously the first one, and then you built on from there. So all the shipwright had to do was lay the plate out and mark it off to those dimensions. And they made a mould to the curve, to whatever curve was required, set it in the shop and it was pressed up to that shape."